Sound Transit
Updated October 13, 2009

Schedule
Sound Transit completed the utility relocations in time for the start of the 2009 football season.  Minor work continues.   The Tunnel contactor is projected to start along the Burke Gilman Trail mid-December 2009 with full site preparation for station tunneling anticipated for early January 2010.   

Sound Transit Executive Summary Schedule October 2009
This schedule represents the current work timelines as projected based on information known to date and is subject to modifications as more information is known. 

Sound Transit
    UW SE Campus Transportation Committee
    
    Sound Transit University Link Light Rail
    
30% Station Design Open House slideshow
   
March 2008 Architectural Commission slideshow (large file 125 MB)
    June 2008 Architectural Commission 60% update slideshow

    September 2008 CUCAC slideshow
    October 2008 Light Rail Commission slideshow

U210 Utility Relocation

U210A Modular Units installation

U220 Issue for Construction (IFC) package for the Station Structural / Civil Work  :

 

U220 Construction Submittals:

 

U250 Design Submission for Station Finishes and Pedestrian Bridge

U260 Design Submission for Track Work and Floating Slab

Terms used in the Summary

In July 2007, a Memorandum Implementation Agreement (MIA) was approved and signed by Sound Transit and the University of Washington, which allows Sound Transit acess to the University's Seattle campus. This MIA supplements a Memorandum of Agreement (MOA) signed by Sound Transit and the University in 2000.

To see a copy of the MIA click here
T
o see a copy of the MOA click here

The proposed alignment of the Sound Transit project under the Seattle campus is shown in this map.

For more information, visit the Sound Transit University Link webpage